Our approach

Study. Plan. Schedule. Control.

A continuous planning cycle that connects project understanding to the baseline, the forecast and the next decision.

StudyUnderstandPlanSequenceControlDecideScheduleConnect
01
Study

Understand the project.

Review scope, methods, known constraints and the information available. Identify interfaces and planning assumptions before they become schedule commitments.

Related expertise
THE WORKING OUTPUT

Planning basis, interface questions and a constraints register.

01Scope02Drawings03Constraints04InterfacesAgreed planning basis
02
Plan

Develop the execution method.

Coordinate work areas, access, procurement and trade handovers. Review the sequence against the field conditions and resource assumptions.

Related expertise
THE WORKING OUTPUT

Execution methodology, work-area sequence and procurement priorities.

PHASED WORK AREASAREA AStructureAREA BFit-outAREA CHandoverAccess shapes the sequence.Crews and supply support it.
03
Schedule

Connect the work to the milestones.

Build the Primavera P6 logic around the execution plan. Review open ends, relationships and the paths that control delivery.

Related expertise
THE WORKING OUTPUT

CPM baseline, optional cost or resource loading, and a schedule narrative.

CONNECTED EXECUTION SEQUENCEDesignProcurementConstructionHandoverEach package connects to delivery.
04
Control

Review progress. Explain the forecast.

Reconcile actual progress, review what changed and identify the decisions needed next. Use recovery and change analysis when the project requires them.

Related expertise
THE WORKING OUTPUT

Progress update, forecast, path analysis and action priorities.

COMPARE. EXPLAIN. ACT.BaselineCurrent forecastNext decision: release the work area.
SCHEDULE COMPLIANCE / A STRONGER SUBMISSION

A good plan should meet the requirements.

Read the specification. Check the schedule. Close the comments. We help your team make submission requirements visible before the package reaches the reviewer.

Explore compliance support
01 / READWhat is required?

Contract criteria, milestones and submission rules.

02 / REVIEWWhat needs attention?

Schedule quality, supporting outputs and gaps.

03 / RESPONDWhat changed?

Comment responses, revisions and rechecks.

The review basis is project-specific. Acceptance remains with the responsible project reviewer.

LEARNING / BRING YOUR TEAM INTO THE THINKING

Build a better plan. Build a stronger team.

Practical workshops that connect construction understanding with scheduling skills. Choose the learning path your team needs.

TRY THE THINKING

One change. A different finish?

Move the procurement delay. Explore the options. See why understanding the driving work matters more than watching a date.

0 days50 days
EXECUTION / SCENARIO EXPLORERILLUSTRATIVE EXAMPLE
DAY 0306090120
Procurement
Civil works
Structure
Equipment
Commissioning
Driving sequenceOther work
98FORECAST FINISH / DAY
0CHANGE FROM BASELINE / DAYS
98BASELINE FINISH / DAY

Workface access sets the installation start. In this example, some procurement delay can fit within the available buffer without moving the finish.

Current driver: Workface access

Illustrative scenario in day units. Fixed construction durations and simplified interfaces. Earlier release and phased access are assumed feasible for this example. These values are not a project forecast or a promised recovery result.

THE COORDINATION BEHIND THE METHOD

Keep decisions connected to actions.

Alongside our planning tools, we use Polaris, developed through Hexifyer, to keep project conversations, information and follow-up connected.

Explore the three stages on the right. Then open the walkthrough below to see how that coordination supports our day-to-day planning work.

PolarisWORKFLOW ILLUSTRATION
01 / KEEP THE CONTEXT

Start with the conversation.

Bring notes, ideas and project information into one workspace.

Meeting noteConfirm access before agreeing the sequence.EXAMPLE COORDINATION ITEM
An example of our workflow, not a live client workspace.
How we use Polaris, our workspace by Hexifyer
THE COORDINATION BEHIND THE PLANNING

Keep the context.
Follow through on the decision.

We developed Polaris through Hexifyer and use it to organize the ideas, meetings, tasks and project information behind our work. It helps keep an agreed next step connected to the conversation that started it.

Capture the context

Keep notes, references and early questions together so the planning discussion has a clear starting point.

Coordinate the conversation

Organize meeting agendas and notes, then retain decisions for the next review.

Follow up on actions

Turn the agreed next step into a task and track its progress with the team.

Keep information connected

Bring relevant documents, links and project context into a shared workspace.

EXAMPLE / FROM DISCUSSION TO FOLLOW-UP

Question: Is the work area ready for the proposed sequence?

Next action: Gather the access information and bring it to the planning review.

Illustrative workflow; client information remains confidential.

Primavera P6 supports our schedule development and analysis. Polaris supports the conversations, information and follow-up around that work.

Polaris walkthrough · starts at 2:42. Watch on YouTube

Explore Polaris